BHSL completes the successful manufacturing of maiden Pelton Runner for BHP (L/S)

Posted on: March 31, 2021

In what could be called an engineering feat, a gigantic milestone in scaling newer heights has been made in the recent time. BHSL has successfully completed the manufacturing of the maiden Pelton Runner for Basochhu Hydropower Plant (BHP), lower stage in December 2020.  

In keeping with the schedule of delivery, due to the Covid-19 pandemic induced travel restriction, the Final Acceptance Test (FAT) has been conducted from 2nd to 5th February, 2021. The FAT was technically cleared and qualified at the site of origin in presence of BHP representatives.